Thursday, October 8, 2009

Construction Set to Go at Gilpins!

This has been a fun week full of good stuff and God's surprises. Mike Cutter of Cutter Construction and I just met to discuss a work schedule of repairing the basement at the Gilpins home! Both the contractor and Mariann Gilpin have signed a contract which is required by Jumpstart to officially begin the project. Cutter Construction was selected during our "bid meeting" with Jumpstart officials earlier this week. Thanks to recommendations from people in our church, we were blessed to find three high quality, highly recommended contractors to bid on the job. Thank you all!!!

We have agreed on the following dates to repair the Gilpins home:

Oct. 19th Probable start date
Oct. 26th Definite start date

Oct. 31st Probable end date
Nov. 6th Definite end date

We are also planning a house blessing on-site and a celebration at the church once the work is completed. Stay tuned for a date and time on that one.